Justice McLAREN delivered the judgment of the court, with opinion.
¶ 1 Plaintiff, Marita Williams Salvi, as successor trustee of the Albert S. Salvi Family Trust (Trust), appeals the dismissal of her claims against defendant the Village of Lake Zurich (Village). Plaintiff's amended complaint alleged that the Village's renovation of a detention pond (Pond) near an office building (Building) on property (Property) owned by plaintiff caused the Pond to overflow during a heavy rain, flooding the bottom floor of the Building. The trial court dismissed the claims as barred by the Local Governmental and Governmental Employees Tort Immunity Act (Tort Immunity Act) (745
¶ 3 Plaintiff filed her amended complaint in January 2014, naming as defendants the Village and the ELA Area Public Library District (Library). She also named several respondents in discovery. The Library and the respondents were dismissed pursuant to a settlement before plaintiff filed her notice of appeal.
¶ 4 The general allegations in the complaint are as follows. Plaintiff was the current trustee of the Trust and the current owner of the Property, which was in the Village and improved with the Building. The Property and the Building were held by the Trust. Prior to 1989, the Federal Deposit Insurance Corporation (FDIC) owned the Property as well as a contiguous parcel, later known as the Good Shepherd Subdivision (Subdivision). In 1989, Albert S. Salvi, plaintiff's predecessor in interest, purchased the Property from the FDIC and placed it with the Trust. The Pond was situated in the Subdivision. The Property "extend[ed] in part onto the slopes of the Pond." At the time of the purchase, "the Pond had no history of overflowing." Sometime after 1989, Good Shepherd Church (Church) purchased the Subdivision from the FDIC. The Subdivision was later divided into four parcels. One parcel was purchased by the Library (Library Parcel) and another parcel by the Village (Village Parcel). The remaining two parcels were retained by the Church. On one of these parcels (Church Parcel), the Church constructed a church building. On the remaining parcel was the Pond (Pond Parcel). All four parcels were located north and west of the Property. The only parcel contiguous to the Property was the Pond Parcel.
¶ 5 In the summer of 2000, the Church, the Village, and the Library signed an "Easement Agreement" (Agreement), a copy of which was attached to the complaint. The Agreement characterized the Pond as a "storm water detention basin * * * serving the storm water management requirements of the Library Parcel, the Village Parcel, the Church Parcel, and the Pond Parcel * * *." The stated purpose of the Agreement was to "permanently protect the establishment, use, and maintenance of the [Pond] for its intended purposes." To this end, the Church granted two types of easements over the Pond Parcel. First, to both the Village and the Library, the Church granted "a perpetual, nonexclusive easement over, across, under, upon, along, and through * * * [the Pond Parcel] * * * for the purpose of discharging storm water into the [Pond]." In connection with the discharge easement, the Village was granted "a perpetual, nonexclusive easement over, across, under, upon, along, and through * * * [the Pond Parcel] * * * for the purpose of maintaining, repairing and replacing the storm water laterals, culverts, drains, and associated laterals, lines, and devices * * *, such work to be at the Village's cost." Second, the Agreement granted the Village "a perpetual, nonexclusive easement over, across, under, upon, along, and through * * * [the Pond Parcel] * * * for the purpose of rehabilitation and maintenance of [the Pond] * * *."
¶ 6 Plaintiff alleged that subsequent improvements to the Village and Library Parcels and renovation of the Pond contravened requirements set forth in the Agreement and in Lake County's Watershed Development Ordinance (Watershed Ordinance) (Lake County Watershed Development Ordinance (amended Aug. 14, 2001)).
¶ 7 We note that, in various places, the complaint describes the Agreement as granting the Village "the perpetual right to possess, manage and control the Pond Parcel." Plaintiff also alleged that the Village "acquired * * * the Pond Parcel," and she characterized the Pond as "the Village's Pond." Though the Village did not file an answer below (having filed a motion to dismiss in lieu of an answer), it challenges on appeal the accuracy of the complaint's description of the Village's interest in the Pond and the Pond Parcel.
¶ 8 The Agreement contains the following provision relating to the Pond's capacity:
The Agreement notes that the Village had approved plans for the construction of a library facility on the Library Parcel and a police station on the Village Parcel. In this connection, the Agreement specifies that "[n]o development of the Village Parcel, the Church Parcel, the Pond Parcel, or the Library Parcel shall be permitted in excess of the Maximum Coverage except only if the Church, the Library, the Village, or other developer of such parcel, as the case may be, shall provide for an increase in the Pond Capacity at such developer's cost and in a manner and amount satisfactory to the Village Engineer, whose approval shall not be unreasonably withheld."
¶ 9 The Agreement not only grants the Village an easement for rehabilitation and maintenance of the Pond, but requires the Village to perform that work when necessary and provides for the sharing of costs associated with the work. The Agreement notes that the Village had submitted to the Church and the Library "a preliminary analysis and estimate of the work related to the rehabilitation and future maintenance of [the Pond]." An attachment to the Agreement sets forth the proposed work, which includes excavation and reshaping of the Pond's slopes.
¶ 10 The Watershed Ordinance was enacted in October 1992 and has since been amended several times. Plaintiff's complaint makes extensive reference to the Watershed Ordinance. The complaint contains two significant block quotations from the Watershed Ordinance. The first is from the "purpose" section of the ordinance (Lake County Watershed Development Ordinance, art. IB. (amended Aug. 14, 2001)). Several specific purposes are listed, including the objectives of preventing flooding and drainage hazards, specifically those stemming from "development," and protecting buildings and improvements from flood damage "to the greatest extent possible." Lake County Watershed Development Ordinance, art. IB.6. (amended Aug. 14, 2001). The complaint also quotes a section stating that "[n]o person, firm, corporation or governmental agency" may commence certain developments without
¶ 11 Following the complaint's quotations from the Watershed Ordinance is a three-page enumerated list of mandates from the Watershed Ordinance. Plaintiff alluded to, inter alia, (1) platting and reporting requirements relating to runoff and base flood elevation (BFE); (2) design dictates for stormwater detention facilities; and (3) limits on detention release rates. After each requirement is a specific citation to a provision of the Watershed Ordinance.
¶ 12 The general allegations of the complaint proceed to state that, in addition to "having the legal duty to comply with" the Watershed Ordinance, the Village and the Library "had a common law duty to refrain from collecting water and discharging it onto [the Property]."
¶ 13 The general allegations go on to describe: (1) the development of the various parcels; (2) the work that the Village performed on the Pond; and (3) the flood that resulted from those activities. The allegations state as follows. In 2002, the Village commenced work on the Pond. The Village knew of its obligations under the Watershed Ordinance but "utterly disregarded the law" in "reconstructing and thereafter maintaining the Pond so that the Pond, upon overflowing, would spill onto" the Property. Subsequent to the Village's work on the Pond, the Village constructed a police station on the Village Parcel and the Library constructed a library facility on the Library Parcel. Both entities made their improvements without "obtain[ing] the necessary permits under [the Watershed Ordinance]," and the Village also "disregarded its own ordinance and [the Agreement] by building a police department with impervious surface coverage in excess of 60%." (As to the Village's alleged violation of "its own ordinance," plaintiff provided more detail in count III against the Village.) Plaintiff alleged that, "[a]s the Village allowed additional private development of [the Subdivision] without compliance with [the Watershed Ordinance] and [the Agreement], the threat of flooding [the Building] grew." In April 2013, "after heavy rains, the shoreline of the Pond crept perilously close to [the Property]." Though the Village placed sandbags "along or near the property line of the Village-controlled Pond and [the Property]," the Pond overflowed on June 26, 2013, spilling water into the lower floor of the Building.
¶ 14 Plaintiff's complaint contains eight counts. Counts I, II, III, VI, and VII named the Village. Count I alleged "willful and wanton trespass," count II alleged "negligent trespass * * * breach of duties imposed by [the Watershed Ordinance]," and count III alleged "negligent trespass * * * breach of common law duties." Counts I through III, like the remaining counts, incorporated all of the general allegations, including the allegation that the development of the Library Parcel contravened the Agreement and the Watershed Ordinance. The allegations specific to counts I through III, however, focused on the Village's rehabilitation of the Pond and the Village's later development of the Village Parcel. Both counts I and II alleged that the rehabilitation and development violated the Agreement and the Watershed Ordinance, but count I alleged that the
¶ 15 Counts I and II alleged that the Village "was able to avoid having its illegal conduct detected by law enforcement authorities, including the Lake County Storm Water Management Commission (SMC), by failing to inform SMC or state authorities of its acquisition of the Pond Parcel, its illegal `rehabilitation' of the Pond, and its later maintenance and repair to the Pond from 2003 through 2013." Plaintiff further alleged that the police station subsequently constructed on the Village Parcel "had an impervious surface area greater than 60%." According to plaintiff, "[t]his development created additional discharge of stormwater flowing into the Pond, making it more likely that [the Property] would become the Pond's spillway." Further, "despite the fact that the Village[`s] development of the surrounding lands made the illegal rehabilitation even more dangerous with the addition of developments that did not comply with legal requirements, the Village never warned [p]laintiff that her property had been made a spillway to accommodate its development." The Village "failed to inspect its Pond, or failed to adequately inspect for the aforesaid violations[,] and the Village never prepared plans compliant with [the Watershed Ordinance], thus making the
¶ 16 Both counts I and II further alleged that, as a direct and proximate result of the Village's "acts and omissions * * * and concealment [of them]," the Pond "received waters from a heavy rain, rose to such a level it would otherwise not have risen, and spilled onto the [Property]."
¶ 17 Count III related the same history concerning the rehabilitation of the Pond, the development of the Village Parcel, and the flooding of the Building. In count III, however, plaintiff asserted liability based on (1) the Village's "common law duties not to cast water upon the property of its neighbor" and (2) the Village's own ordinances. Plaintiff alleged the following specific breaches or violations:
The balance of count III repeated essentially the same allegations contained in counts I and II.
¶ 18 Count VI asserted "plaintiff third party beneficiary — breach of contract" based on the following violations of the Agreement:
Plaintiff alleged that, as a direct and proximate result of these breaches, the Pond overflowed and flooded the Building.
¶ 19 In count VII, the last of the five counts against the Village, plaintiff sought a writ of mandamus directing the Village to take the following actions to bring the Village Parcel and the Pond into compliance with the Agreement and the Watershed Ordinance:
¶ 20 The Village filed a hybrid motion to dismiss all counts against it, pursuant to section 2-619.1 of the Code of Civil Procedure (Code) (735 ILCS 5/2-619.1 (West 2014)). The Village made several contentions that plaintiff's complaint failed to state a cause of action and so should be dismissed under section 2-615 of the Code (735 ILCS 5/2-615 (West 2014) (dismissal of claims because of a legal deficiency appearing on the face of the complaint)). One such contention was that, under the public-duty rule, the Village owed plaintiff no duty of care in connection with the matters plaintiff alleged. See Zimmerman v. Village of Skokie, 183 Ill.2d 30, 32, 231 Ill.Dec. 914, 697 N.E.2d 699 (1998) ("The public duty rule is a long-standing precept which establishes that a governmental entity and its employees owe no duty of care to individual members of the general public to provide governmental services, such as police and fire protection."). The Village also cited, as "affirmative matter avoiding the legal effect of or defeating [plaintiff's] claim[s]" (735 ILCS 5/2-619(a)(9) (West 2014)), four provisions of the Tort Immunity Act (745 ILCS 10/1-101 et seq. (West 2014)). The Village cited sections 2-103, 2-104, 2-202, and 3-105 of the Tort Immunity Act (745 ILCS 10/2-103, 2-104, 2-202, 3-105 (West 2014)).
¶ 21 Plaintiff filed a motion to reconsider. This, too, was brought to hearing but there is no transcript in the record. In its written order denying the motion, the court found all claims against the Village barred because "the flood was an act of God; the tort immunity cited by [the Village] immunized the Village from liability."
¶ 22 Plaintiff filed this timely appeal.
¶ 25 Plaintiff challenges the dismissal of her first amended complaint. The Village's hybrid motion under section 2-619.1 of the Code invoked the standards of section 2-615 and section 2-619 of the Code. A motion to dismiss under section 2-615 of the Code challenges the legal sufficiency of a complaint, based on defects apparent on its face. Marshall v. Burger King Corp., 222 Ill.2d 422, 429, 305 Ill.Dec. 897, 856 N.E.2d 1048 (2006). In contrast, a motion to dismiss pursuant to section 2-619 admits the legal sufficiency of the complaint but asserts some other matter that defeats the claim. Patrick Engineering, Inc. v. City of Naperville, 2012 IL 113148, ¶ 31, 364 Ill.Dec. 40, 976 N.E.2d 318. For instance, subsection (a)(9) of section 2-619 provides for dismissal of a claim that is "barred by * * * affirmative matter avoiding the legal effect of or defeating the claim" (735 ILCS 5/2-619(a)(9) (West 2014)). An "affirmative matter" under section 2-619(a)(9) is "`something in the nature of a defense which negates the cause of action completely * * *.'" Van Meter v. Darien Park District, 207 Ill.2d 359, 367, 278 Ill.Dec. 555, 799 N.E.2d 273 (2003) (quoting Illinois Graphics Co. v. Nickum, 159 Ill.2d 469, 486, 203 Ill.Dec. 463, 639 N.E.2d 1282 (1994)). Here, the trial court held that plaintiff's claims were barred by the Tort Immunity Act. The immunity granted by the Tort Immunity Act is an affirmative matter properly raised in a section 2-619(a)(9) motion to dismiss. Id. We review de novo the dismissal of a complaint pursuant to section 2-619(a)(9). Smith v. Waukegan Park District, 231 Ill.2d 111, 115, 324 Ill.Dec. 446, 896 N.E.2d 232 (2008).
¶ 26 Our threshold task is to clarify the distinctions, as we see them, among the five counts against the Village. We are prompted to do so by the parties' disagreement over whether, as the trial court assumed, the Tort Immunity Act applies to all five counts. The parties' specific quarrel is over the proper characterization of counts VI and VII.
¶ 27 Section 2-101 of the Tort Immunity Act (745 ILCS 10/2-101 (West 2014)) clarifies the kinds of claims to which its immunity applies. First, "[n]othing in this Act affects the right to obtain relief other than damages against a local public entity or public employee." Id. Second, "[n]othing in this Act affects the liability, if any, of a local public entity or public employee, based on * * * [c]ontract." 745 ILCS 10/2-101(a) (West 2014).
¶ 28 The Village claims that counts VI and VII are properly construed as having tort elements, because they allege (either directly or by incorporation of the complaint's general allegations) that the Village had a legal duty to comply with the Watershed Ordinance and with common-law restraints on water drainage. The Village is mistaken. First, whether count VII has tort elements is inapposite to whether the Tort Immunity Act applies, because the relief sought is not damages but a writ of mandamus. Cf. People ex
¶ 29 The Village, however, proposes independent grounds for sustaining the dismissal of counts VI and VII. We will consider them below. At present, we examine the dismissal of counts I through III, which are the tort claims.
¶ 31 As we turn to counts I through III, we note that they overlap with count VI in the further respect that each alleges violations of the Agreement in connection with the development of the parcels surrounding the Pond. However, in counts I through III, the allegations regarding the Agreement appear mostly by incorporation of the general allegations, the sole reference among the counts' specific allegations being a comment that the police station built by the Village had "impervious surface area greater than 60%." As this allegation is ancillary to counts I through III but is the focus of count VI, our consideration of the Agreement is reserved for our discussion of count VI.
¶ 32 The conduct at issue in counts I through III is: (1) the Village's development and maintenance of the Pond; (2) the Village's development of the Village Parcel; and (3) the Library's development of the Library Parcel, which the Village "allowed." Counts I and III allege negligence and count II alleges willful and wanton conduct. For standards of care, counts I and II cite the Watershed Ordinance, while count III cites both the Village's own ordinances and common-law standards.
¶ 33 The trial court found all three counts barred by the Tort Immunity Act. The Village defends the finding of immunity but also proposes an alternative basis for affirming the dismissal. As it did below in moving for dismissal, the Village contends that it did not owe plaintiff a duty of care. This is a question distinct from, and precedent to, the question of whether the Tort Immunity Act applies. "The distinction between an immunity and a duty is crucial, because only if a duty is found is the issue of whether an immunity or defense is available to the governmental entity considered * * *." Zimmerman, 183 Ill.2d at 46, 231 Ill.Dec. 914, 697 N.E.2d 699.
¶ 34 In general, unless an immunity provision applies, municipalities are liable in tort to the same extent as private parties. Van Meter, 207 Ill.2d at 368-69, 278 Ill.Dec. 555, 799 N.E.2d 273. Thus, in Van Meter, our supreme court held that the common-law duty not to increase the natural flow of surface water onto the property of adjacent landowners applied to both private and public landowners. See id. at 369, 278 Ill.Dec. 555, 799 N.E.2d 273; see also Gass v. Metro-East Sanitary District, 186 Ill.App.3d 1077, 1092-93, 134 Ill.Dec. 722,
¶ 35 The Village also argues that every count directed against the Village is premised largely upon the Watershed Ordinance; however, the Watershed Ordinance prohibits using its terms to create liability. Article VIII of the ordinance, entitled "DISCLAIMER OF LIABILITY," states:
Thus, according to the Village, liability cannot be created against it under the Watershed Ordinance.
¶ 36 We disagree. The Watershed Ordinance states that its provisions "shall not create liability * * * for any claims, damages or liabilities that result from reliance on this Ordinance or any administrative decision lawfully made thereunder." (Emphasis added.) Id. Plaintiff alleges that her damages arose, not because the Village relied on the Watershed Ordinance and made decisions based on its requirements, but because the Village ignored the ordinance, did not follow its strictures, and did not lawfully make administrative decisions pursuant to it. The disclaimer of liability seeks to protect governmental entities that follow the Watershed Ordinance's requirements, not those who ignore them. Therefore, the disclaimer does not bar liability on the part of the Village.
¶ 37 The Village also invokes the public-duty rule as a basis for finding no duty of care, arguing that, under the rule, a municipality and its employees owe no duty to provide an individual citizen with specific municipal services such as police and fire protection, or to enforce local laws and building codes. See Belton v. Forest Preserve District, 407 Ill.App.3d 409, 426, 347 Ill.Dec. 931, 943 N.E.2d 221 (2011). However, our supreme court has recently abolished the public-duty rule. See Coleman v. East Joliet Fire Protection District, 2016 IL 117952, 399 Ill.Dec. 422, 46 N.E.3d 741. Thus, we will proceed to the Tort Immunity Act.
¶ 38 The Tort Immunity Act "serves to protect local public entities and public employees from liability arising from the operation of government." Van Meter, 207 Ill.2d at 368, 278 Ill.Dec. 555, 799 N.E.2d 273. "By providing immunity, the General Assembly sought to prevent the dissipation of public funds on damage
¶ 39 In its motion to dismiss, the Village cited four sections of the Tort Immunity Act and now relies on those same sections. They are sections 2-103, 2-104, 2-206, and 3-105 (745 ILCS 10/2-103, 2-104, 2-206, 3-305 (West 2014)). Section 2-103 provides: "A local public entity is not liable for an injury caused by adopting or failing to adopt an enactment or by failing to enforce any law" (745 ILCS 10/2-103 (West 2014)).
¶ 40 Denying that section 2-103 applies here, plaintiff notes that the dictionary definition of "enforce" is "[t]o give force or effect to (a law etc.); to compel obedience to" (Black's Law Dictionary 549 (7th ed.1999)). See People v. Dabbs, 239 Ill.2d 277, 288, 346 Ill.Dec. 484, 940 N.E.2d 1088 (2010) (dictionary definitions may be consulted to determine the plain and ordinary meaning of a statutory term). Plaintiff concludes from this definition that:
¶ 41 Plaintiff presses here a distinction between nonenforcement and non-compliance. We agree with this distinction. The distinction existed before the Tort Immunity Act's passage in 1965. The common law has long distinguished, for liability purposes, between (1) injuries tied to a local public entity's passivity and (2) injuries tied to its activity. For instance, our supreme court has observed that section 2-103 codifies (at least in part) the common-law public-duty rule, namely, that "municipalities are not liable in tort to members of the general public for failure to enforce local laws or ordinances." Burdinie v. Village of Glendale Heights, 139 Ill.2d 501, 507-08, 152 Ill.Dec. 121, 565 N.E.2d 654 (1990) (citing Ill. Rev. Stat. 1989, ch. 85, ¶ 2-103), overruled on other grounds by Coleman, 2016 IL 117952, 399 Ill.Dec. 422, 46 N.E.3d 741. Although the public-duty rule was recently abolished by the supreme court (see generally Coleman, 2016 IL 117952, 399 Ill.Dec. 422, 46 N.E.3d 741), this did not impact its codification in section 2-103.
¶ 42 Failure to enforce local laws or ordinances was not the only kind of passivity that the common law generally insulated from liability. A municipality has no duty under the common law to make public improvements. West v. Kirkham, 147 Ill.2d 1, 14, 167 Ill.Dec. 974, 588 N.E.2d 1104
¶ 43 Section 3-103(a) of the Tort Immunity Act codifies this common-law duty of care in the making of public improvements. 745 ILCS 10/3-103(a) (West 2014). Section 3-103(a) insulates a local public entity from liability "for an injury caused by the adoption of a plan or design of a construction of, or an improvement to public property," but it states that the entity will be liable "if after the execution of such plan or design it appears from its use that it has created a condition that is not reasonably safe." Id. The liability recognized here stems from the public entity's activity (which might involve noncompliance with an enactment). Section 3-103(a) buttresses the conclusion that what the legislature meant to insulate by way of section 2-103 was strictly the passivity of nonenforcement.
¶ 44 Plaintiff does not allege merely that the Village failed to stop other parties from violating the Watershed Ordinance and causing water to spill onto the Property. Instead, plaintiff alleges that the Village itself failed to follow the Watershed Ordinance and was therefore liable for the damage to the Property when the Pond overflowed its banks. Paragraph 50 of count I and paragraphs 51 of counts II and III list 12 specific failures of the Village to follow the strictures of the Watershed Ordinance as it related to the reconstruction of the Pond, and plaintiff also raises allegations regarding the development of the Village Parcel as it related to excess impervious surface area and the reconstruction of the Pond such that it became a spillway onto the Property. These allegations have nothing to do with failing to enforce the law; they have everything to do with failing to follow the law. Thus, section 2-103 provides no immunity to the Village.
¶ 45 Sections 2-104 and 2-206 of the Tort Immunity Act grant immunity to local public entities and public employees for injuries caused by the issuance, denial, suspension, or revocation of, or by the failure or refusal to issue, deny, suspend, or revoke, any permit, license, certificate, approval, order, or similar authorization where the entity or employee is authorized by enactment to determine whether the authorization should be issued, denied, suspended, or revoked. See 745 ILCS 10/2-104 (entities), 2-206 (employees) (West 2014).
¶ 46 We conclude that sections 2-104 and 2-106 of the Tort Immunity Act provide no immunity to the Village. Plaintiff does not allege that the Village or any of its employees improperly determined whether some "permit, license, certificate, approval, order or similar authorization"
¶ 47 We next consider the immunity provided by section 3-105(a) of the Tort Immunity Act, which provides:
According to the Village, plaintiff's complaint "clearly alleges that it was a heavy rain that ultimately caused the water to overflow into the pond." The Village then argues that "[d]amages caused by the effect of weather conditions, which specifically includes rain, are immunized pursuant to Section 3-105." Further, the Village avers, there are no exceptions to the section 3-105 immunity, and plaintiff is asking this court "to create exceptions for the weather conditions when the legislature has not." We disagree.
¶ 48 We first note that section 3-105(a) provides immunity for injuries caused by the "effect of weather conditions as such on the use of streets, highways, alleys, sidewalks or other public ways, or places, or the ways adjoining any of the foregoing." Id. However, the damage in this case was not alleged to have been caused by the effect of weather on streets or sidewalks. Plaintiff alleged that the flooding of the Building was caused by the Village's errors in reconstructing the Pond and in developing the Village Parcel near the Pond. The classic applications of section 3-105 are to accumulations of snow or ice on streets and sidewalks (see, e.g., Ziencina v. County of Cook, 188 Ill.2d 1, 241 Ill.Dec. 610, 719 N.E.2d 739 (1999); Rios v. City of Chicago, 331 Ill.App.3d 763, 265 Ill.Dec. 71, 771 N.E.2d 1030 (2002)) and to defective streets and sidewalks (see, e.g., Horton v. City of Ottawa, 40 Ill.App.3d 544, 352 N.E.2d 23 (1976)). We fail to see how section 3-105 applies here, and we conclude that section 3-105 provides no immunity to the Village.
¶ 49 We also note that, in denying plaintiff's motion to reconsider, the trial court remarked that "the flood was an act of God; the tort immunity cited by [the Village] immunized the Village from liability." Perhaps "act of God" was a reference to section 3-105 of the Tort Immunity Act. Perhaps "act of God" was a reference to the common-law doctrine of that name. "`A loss or injury is due to the act of God[ ] when it is occasioned exclusively by natural causes such as could not be prevented by human care, skill[,] and foresight.'" Evans v. Brown, 399 Ill.App.3d 238, 246, 339 Ill.Dec. 144, 925 N.E.2d 1265 (2010) (quoting Wald v. Pittsburgh, Cincinnati,
¶ 50 How the trial court came to rely on the "act of God" doctrine, if indeed it did, is perplexing, because the Village did not raise the doctrine in its pleadings. The Village might have raised it at one or both of the hearings on the pleadings, or the court might have raised it sua sponte. We do not know, because plaintiff has included neither transcript in the record on appeal. Where, as here, the standard of review is de novo, the reviewing court may proceed without a record of the trial court's reasons. Friedl v. Airsource, Inc., 323 Ill.App.3d 1039, 1042 n. 2, 257 Ill.Dec. 459, 753 N.E.2d 1085 (2001). However, it is always helpful to know the reasons, if any, given by the trial court, and, in this case, the transcripts might well have explained the "act of God" reference in the written order.
¶ 52 We turn to counts VI and VII. As discussed, the trial court erred by finding them barred by the Tort Immunity Act. The Village, however, proposes alternative grounds for affirming the dismissal. "It is well settled that a reviewing court is not bound by the reasons given for a trial court's judgment and may affirm on any basis supported by the record regardless of whether the trial court relied on the same basis." Schultz v. Schultz, 297 Ill.App.3d 102, 106, 231 Ill.Dec. 598, 696 N.E.2d 1169 (1998). The Village's contentions on these counts go to the sufficiency of the allegations. See 735 ILCS 5/2-615 (West 2014).
¶ 53 Count VI alleged breach of contract against the Village, with plaintiff as a third-party beneficiary. According to count VI, "the primary purpose of the Easement Agreement was and now remains to benefit the Plaintiff, the Pond Parcel and the * * * Property." The Village contends that plaintiff, who was not a party to the Agreement, was not a third-party beneficiary either, and so has no right to sue under the Agreement. "`The well-established rule in Illinois is that if a contract is entered into for the direct benefit of a third person, the third person may sue for a breach of the contract in his or her own name, even though the third person is a stranger to the contract and the consideration.'" Barba v. Village of Bensenville, 2015 IL App (2d) 140337, ¶ 21, 390 Ill.Dec. 917, 29 N.E.3d 1187 (quoting Olson v. Etheridge, 177 Ill.2d 396, 404, 226 Ill.Dec. 780, 686 N.E.2d 563 (1997)). In contract interpretation, however, there is a strong presumption that the contracting parties did not intend to confer benefits on noncontracting parties. Id. ¶ 22. Illinois law recognizes two types of third-party beneficiaries: intended and incidental. Hacker v. Shelter Insurance Co., 388 Ill.App.3d 386, 394, 327 Ill.Dec. 433, 902 N.E.2d 188 (2009). Only an intended third-party beneficiary may enforce rights under a contract. Bank of America National Ass'n v. Bassman FBT, L.L.C., 2012 IL App (2d) 110729, ¶ 27, 366 Ill.Dec. 936, 981 N.E.2d 1. It is not enough that a third party will reap incidental benefits from the contract; the benefit must instead be intended. F.H. Paschen/S.N. Nielsen, Inc. v. Burnham Station, L.L.C., 372 Ill.App.3d 89, 96, 309 Ill.Dec. 865, 865 N.E.2d 228 (2007). Intent to benefit a third party is to be determined from the
¶ 54 Here, having no extrinsic evidence of the circumstances surrounding the execution of the Agreement, we concentrate on the language of the document. The parties to the Agreement are the Church, the Library, and the Village, all owners of parcels contiguous to, or one lot removed from, the Pond Parcel. The Agreement recites that the Pond "was designed and constructed to accommodate maximum storm water flows (the `Pond Capacity') from the Library Parcel, the Village Parcel, the Church Parcel, and the Pond Parcel." Further, the parties have used the Pond for stormwater detention and their intent is to "permanently protect the establishment, use, and maintenance of [the Pond] for its intended purposes." The Agreement contemplates future development of the parties' parcels and requires that they maintain a limit of 60% impervious surface coverage. The Agreement does not mention plaintiff, the Building, or the Property. The Agreement's one mention of nonparties is the following: "In protecting the function of [the Pond], the Village shall not approve or permit additional or increased storm water discharge into [the Pond] by or for the benefit of any user not a party to this Agreement beyond use which currently exists." By this provision, the Village is required to limit the stormwater discharge of nonparties. There is no indication, however, of an intent to benefit anyone but the parties to the Agreement.
¶ 55 Plaintiff contends that, nonetheless, she is a third-party beneficiary of the Agreement:
Here plaintiff cites the contiguity of the Property to the Pond Parcel, but it is not enough under the law that plaintiff would reap an incidental benefit from the Agreement. Indeed, the very contiguity of the Property to the Pond Parcel supports the inference that the failure to mention the Property was deliberate. At the very least, plaintiff, who has the burden on this issue, has not established that the inference is unreasonable. Consequently, since the Agreement contains nothing that is "`practically an express declaration'" (Barba, 2015 IL App (2d) 140337, ¶ 22, 390 Ill.Dec. 917, 29 N.E.3d 1187 (quoting F.H. Paschen/S.N. Nielsen, Inc., 372 Ill.App.3d at 96, 309 Ill.Dec. 865, 865 N.E.2d 228)) of an intent to confer a benefit on plaintiff, we hold that she has failed to plead her status as a third-party beneficiary. Therefore, the dismissal of count VI was not in error. We note that, though the trial court dismissed the count with prejudice, the court neither ruled on nor considered whether the complaint stated a cause of action — or whether, assuming that legal insufficiency was found, the dismissal should be with or without prejudice. The
¶ 56 As for count VII, the Village contends that it does not state a cause of action for mandamus. "Mandamus is an extraordinary remedy to enforce the performance of official duties by a public officer where no exercise of discretion on his part is involved." Wilson v. Quinn, 2013 IL App (5th) 120337, ¶ 18, 376 Ill.Dec. 874, 1 N.E.3d 586. "For a complaint seeking mandamus to withstand a challenge to its legal sufficiency, it must allege facts which establish a clear right to the relief requested, a clear duty of the respondent to act, and clear authority in the respondent to comply with the writ." Id. Further, there must be no other adequate remedy. Cordrey v. Prisoner Review Board, 2014 IL 117155, ¶ 18, 386 Ill.Dec. 660, 21 N.E.3d 423; People ex rel. Madigan v. Snyder, 208 Ill.2d 457, 465, 281 Ill.Dec. 581, 804 N.E.2d 546 (2004).
¶ 57 First, we note that plaintiff has another adequate remedy. We have already held that plaintiff's counts sounding in tort are not barred by the Tort Immunity Act; thus, as plaintiff's trespass counts are viable, mandamus will not lie.
¶ 58 We also note that plaintiff's mandamus count fails for other reasons. Plaintiff's prayer for relief in that count asks that the Village be ordered to perform the following acts:
¶ 59 Other than the relief requested in subparagraph C, all of the requested relief involves the exercise of discretion. Redesigning, constructing, modifying, building, and reconstructing are actions that require vast numbers of decisions to be made by large numbers of individuals exercising their judgment and discretion and are not the types of actions susceptible to an order of mandamus.
¶ 60 Further, the Village's actions regarding the reconstruction and maintenance of the Pond were not the performance of official duties by a public officer. The Pond Parcel is owned by the Church; the Village rehabilitated and maintained the Pond, not in its official capacity as a municipal corporation, but because of its status as a party to the Agreement. This activity did not arise from a duty the Village owed to the general public; it is more akin to the actions of a neighbor "`who so piles sand close to his boundary that by force of gravity alone it slides down onto his neighbor's land, or who so builds an embankment that during ordinary rainfalls the dirt from it is washed upon adjacent lands,'" or who "`erects a dam across a stream, thereby intentionally causing the water to back up and flood'" another's
¶ 62 For the foregoing reasons, we affirm the trial court's dismissal with prejudice of count VII. We affirm the dismissal of count VI, but we vacate the finding of prejudice attached to the dismissal. We reverse the trial court's dismissal of counts I, II, and III, and we remand the cause for further proceedings.
¶ 63 Affirmed in part and reversed in part.
¶ 64 Cause remanded.
Justices HUDSON and BIRKETT concurred in the judgment and opinion.